September 27, 2003
Aluminum soffit work is completed on The Horizon Model Center.
September 23, 2003
Interior insulation is completed on The Horizon Model Center.
September 18, 2003
Roof shingles are installed on The Horizon Model Center.
September 16, 2003
Electrical wiring is completed for The Horizon Model Center.
September 12, 2003
Plumbing lines are installed in The Horizon Model Center.
September 10, 2003
HVAC ductwork completed on The Horizon Model Center.
September 8, 2003
Brigon Homes is pleased to announce "The Jewel," our newest home design. Features included in The Jewel will be posted soon. In the meantime, please feel free to review the floorplan and elevation sketches for this new home by clicking on the picture below.
September 8, 2003
Concrete pool foundation installed for The Horizon Model Center.
September 5, 2003
Windows and exterior doors installed on The Horizon Model Center.
September 3, 2003
Interior framing of The Horizon Model Center is completed.
|